Labour charge of concrete works

2014 Cost of concrete work labour charge in India Kerala

Sl No Item of work Unit Labour charge Unit Labour charge
1a Slab up to 10 cm thick m2 RS 538.00 ft2 RS 50.00
1b Slab above 10 cm thick m3 Rs.5300.00 ft3 Rs.150.00
2 P.c.c-FLOOR m2 RS 215 F2 RS 20.00
3 Footing m3 RS 4700.00 Qft RS 133.00
4 Concrete wall (10 cm) m2 RS 592.00 Sqft RS 55.00



5 Rack.Plain Sunshade m2 RS 538.00 Sqft RS 50.00
6 Sunshade Slope m2 RS 650.00 Sqft RS 60.00
7 Board work m2 RS 592.00 Sqft RS 55.00
8 Hanging(drop board) Board (30 cm) Rm RS 180.00 Sqft RS 55.00
9 Slope Slab 2 side up to 40 degree m2 RS 710.00 Sqft RS 66.00
10 Slope Slab 2 side 40 to 50 slope m2 RS 770.00 Sqft RS 72.00
11 Slope Slab 3,4 side slope m2 RS 900.00 Sqft RS 84.00
12 Pillar R.Meter RS 650.00 R.feet RS 200.00
13 Pillar 30 cm to 50 cm R.Meter RS 853.00 R.feet RS 260.00
14 Pillar round 20 cm to 30 cm R.meter Rs 853.00 R.fteet Rs.260.00
15 Cutting ordinary (Sunshade Slab) R.meter RS 165.00 R. feet RS 50.00



16 Cutting Round R.meter RS 412.00 R. feet RS 125.00
17 Beam (20 X 30 CM) R.meter RS 600.00 R. feet RS 180.00
18 Beam (30 x 60 cm) R.meter RS 850.00 R. feet RS 260.00
19 Beam arch (20 to 30 cm) R.meter Rs.1000.00 R. feet Rs.310.00
20 Beam Concealed 30 cm Steel Work R.meter RS 100.00 R. feet RS 31.00
21 Beading (Curb ) R.meter RS 132.00 R. feet RS 40.00
22 Belt (15 x 30 cm) R.meter RS 250.00 R. feet RS 76.00
23 Lintel R.meter RS 295.00 R. feet RS 90.00
24 Step (ordinary) 1.00 m width Per step Rs.550.00 —-
25 Step (chain) 1.00 m width Per step Rs.800.00 —-
26 Step (design) 1.00 m width Per step Rs.1250.00 —-



Commercial

1a Slab (10 cm thick) m2 RS 592.00 Sqft RS 55.00
1b Slab above 10 cm m3 Rs 5830 ft3 Rs 165.00
2 Footing m3 RS 4700.00 Qft RS 133.00
3 P.C.C m3 RS 2472.00 Qft RS 70.00
4 Pillar-20 x 40 cm R.Meter RS 650.00 Rqft RS 200.00
5 Pillar Round (upto 30 cm) R.Meter RS 820.00 Rqft RS 250.00
6 Board Work m2 RS 710.00 Sqft RS 66.00
7 Beam ( upto 20×30 cm) R.meter RS 738.00 R. feet RS 225.00
8 Stair (ordinary) 1.25 m width Per step RS 600.00
9 Stair (chain) 1.25 m width Per step RS 900.00
10 Stair (design) 1.25 m width Per step RS 1350.00



2012-Cost of concrete work labour charge in India Kerala

Sl No Item of work Unit Labour charge Unit Labour charge
1 Slab up to 10 cm thick m2 RS 431 ft2 RS 40.00
2 p.c.c m3 RS 1590.00 Qft RS 45.00
3 Footing m3 RS 3532.00 Qft RS 100.00
4 Concrete wall (10 cm) m2 RS 528.00 Sqft RS 50.00
5 Rack m2 RS 484.00 Sqft RS 45.00
6 Plain Sunshade m2 RS 484.00 Sqft RS 45.00



7 Sunshade Slope m2 RS 592.00 Sqft RS 55.00
8 Board work m2 RS 538.00 Sqft RS 50.00
9 Han gin Board (30 cm) m2 RS 753.00 Sqft RS 70.00
10 Slab 2 side 30 to 40 slope m2 RS 645.00 Sqft RS 60.00
11 Slab 2 side 40 to 50 slope m2 RS 699.00 Sqft RS 65.00
12 Slab 3,4 side slope m2 RS 860.00 Sqft RS 80.00
13 Pillar,Beam, Lintel Sq.Meter RS 540.00 Sqft RS 50.00
14 Pillar Round Sq.Meter RS 970.00 Sqft RS 90.00
15 Cutting Sunshade Slab R.meter RS 148.00 R. feet RS 45.00



16 Cutting Round R.meter RS 412.00 R. feet RS 125.00
17 Beam (20 X 30 CM) R.meter RS 544.00 R. feet RS 165.00
18 Beam Arch (20 x 30 cm) R.meter RS 825.00 R. feet RS 250.00
19 Beam Concealed 30 cm Steel Work R.meter RS 270.00 R. feet RS 25.00
20 Beading (Curb ) R.meter RS 132.00 R. feet RS 40.00
21 Lintel (20 cm to 20 cm) R.meter RS 260.00 R. feet RS 80.00
22 Belt (15 x 30 cm) R.meter RS 231.00 R. feet RS 70.00
23 Step (ordinary) 1.00 m width Per step —– —- RS 500.00
24 Step (chain) 1.00 m width Per step —- —- RS 800.00
25 Step (design) 1.00 m width Per step —- —- RS 1200



1 Slab (10 cm thick) m2 RS 538.00 Sqft RS 50.00
2 Footing m3 RS 3532.00 Qft RS 100.00
3 P.C.C m3 RS 2472.00 Qft RS 70.00
4 Pillar Sq.Meter RS 540.00 Sqft RS 50.00
5 Pillar Round Sq.Meter RS 1075.00 Sqft RS 100.00
6 Board Work m2 RS 538.00 Sqft RS 50.00



7 Beam ( upto 23×40 cm) R.meter RS 495.00 R. feet RS 150.00
8 Stair (ordinary) 1.00 m width Per step RS 550.00
9 Stair (chain) 1.00 m width Per step RS 900.00
10 Stair (design) 1.00 m width Per step RS 1300.00



63 Views
Ask a question: Do you have any question related to Labour charge of concrete works. Post here, you will get the best answer from best provider.

Leave a Reply

Your email address will not be published. Required fields are marked *

PAGE ID - 493

www.a2z4home.com mail id : a2z4home@gmail.com, All right reserved